![]() Installation GuideFresh concrete should not be allowed to dry out quickly. The following curing procedure is recommended:
If there is a risk of frost the concrete should be protected with an insulation quilt between weighted down plastic sheets or with a layer of sand. Concrete can take foot or light weight wheeled traffic after 3 or 4 days, but should not be trafficked by cars for at least 1 week and for up to 2 weeks in cold weather. Up to 4 weeks may be required for very heavy vehicles such as fuel lorries. |